Midleton Flood Relief Scheme

Home > Project Information

Project Programme

The project will comprise five stages, as set out below:

Stage I Development of a number of flood relief options and the identification of a preferred Scheme Complete by Spring 2019
Stage II Public Exhibition of Scheme Complete by Summer 2020
Stage III Detailed Design, Confirmation and Tender Complete by 2021
Stages IV and V Construction and Handover of the Works Commence Summer 2021

The Key Public Consultation Dates are as follows:

Public Consultation Day No. 1: Constraints Stage 23rd March 2017
Public Consultation Day No. 2 Emerging Preferred Option Spring 2019
Public Consultation Day No. 3 Statutory Exhibition of Scheme Winter 2019

The main elements of each stage are described below:

Stage I - Scheme Development


Stage II - Public Exhibition


Stage II Alternative – Part 10 Planning


Stage III - Detailed Design, Confirmation and Tender


Stages IV and V - Construction and Handover of the Works

 

Study Area

The study area consists of the Owenacurra and Dungourney Rivers and their tributaries.


Latest news

Ground Investigation more

Summary of Findings from 1st Public Information Day more

Japanese Knotweed Treatment more

Geophysical Survey more

Japanese Knotweed. more

LiDAR survey complete. more

Geophysics, Hydrographic and LiDAR Surveys more

Midleton Flood Relief Scheme - Public Information Day 1 more

Municipal District Meeting presentation more